Lower Level: AV/IT rough in ongoing, furniture backing starting
Second Level: Framing complete, MEP Overhead complete, in wall MEP complete. Handrails and stair welding ongoing, 95% complete. AV/IT rough in ongoing, furniture backing starting
Third Level: Framing 75% complete, MEP Overhead 90% complete, in wall MEP 90% complete Handrails and stair welding