Food Service Progress Report Through March 31, 2015

All the grading has been completed as well as the underground utilities. The slab has been placed and the steel erection and metal decking are complete. Roofing to begin along with the interior framing and in-wall rough utilities. Awaiting the pizza oven delivery. Once received it will be framed in.

 