Student Success Progress Report Through July 30, 2015

Home/Student Success/Student Success Progress Report Through July 30, 2015

Lower Level: AV/IT rough in ongoing, furniture backing starting

Second Level: Framing complete, MEP Overhead complete, in wall MEP complete. Handrails and stair welding ongoing, 95% complete. AV/IT rough in ongoing, furniture backing starting

Third Level: Framing 75% complete, MEP Overhead 90% complete, in wall MEP 90% complete Handrails and stair welding ongoing, 95% complete. AV/IT rough in ongoing, furniture backing starting

Roof Level: HVAC units installed and sealed, roofing precon meeting on 8/6, roofing to start on 8/10.

Exterior: Soffits and wall framing complete, MEP rough in 10% complete

Site: Site/Seat walls complete, waterproofing of walls complete, backfill of walls to be complete end of August with site prep. Power loop and gear tie in to occur on weekend Campus shutdown on 8/7